CRITICAL PATH ANALYSIS FOR: P&L CONSTRUCTION PROJECT RUN DATE: OCT 28 , 1983
TIME PERIOD = CALENDAR DAYS
ACTIVITY DESCRIPTION FROM TO EST. ACTUAL EARLY LAST EARLY LAST FLOAT C REPORT SUBCONTRACTOR
NODE NODE TIME TIME START START FINISH FINISH TIME P FINISH NAME
MOBILIZATION 500 510 2 2 OCT4883 OCT4883 NOV1983 NOV1983 0 * WILSON
GRADE & CLEAR 510 520 5 5 NOV1983 NOV1983 NOV2483 NOV2483 0 * JONES
REBAR PIERS 520 530 5 5 NOV2483 NOV2483 NOV2983 NOV2983 0 * MILLER
POUR PIERS 530 550 5 5 NOV2983 NOV2983 DEC0483 DEC0483 0 * ARCHS
EXCAVATE FOUNDATIONS 550 560 8 8 DEC0483 DEC0483 DEC1283 DEC1283 0 * LEMON
REBAR FOUNDATIONS 560 570 5 5 DEC1283 DEC1283 DEC1783 DEC1783 0 * BUGMAN
ANCHOR BOLTS 570 580 2 2 DEC1783 DEC1783 DEC1983 DEC1983 0 * SHECK
POUR & CURE FOUNDATIONS 580 585 0 0 DEC1983 DEC1983 DEC1983 DEC1983 0 * WILLIS
STRUCTURAL STEEL 585 587 0 0 DEC1983 JAN0384 DEC1983 JAN0384 15 MEAD
DECK FILL CONCRETE 590 600 15 15 JAN1384 JAN1384 JAN2884 JAN2884 0 * KNOUS
WELD STRUCTURAL 587 595 20 20 DEC1983 FEB2584 JAN0884 MAR1684 68 HOM
FIRE PROOFING 620 625 5 5 JAN2884 FEB2884 FEB0284 MAR0484 31 HEDIN
PRECAST PANELS 625 650 20 20 FEB0284 MAR0484 FEB2284 MAR2484 31 ROBER
P.M. FRAMES 600 790 2 2 JAN2884 FEB1584 JAN3084 FEB1784 18 MAST
WALL FRAMING 600 790 20 20 JAN2884 JAN2884 FEB1784 FEB1784 0 * JONEY
SHEET METAL DUCTWORK 600 955 40 40 JAN2884 FEB1184 MAR0884 MAR2284 14 FURRER
ELEC. RGH. IN 620 640 10 10 JAN2884 JAN2884 FEB0784 FEB0784 0 * MACFORD
MAIN ELEC PANEL 640 790 10 10 FEB0784 FEB0784 FEB1784 FEB1784 0 * MCCALL
PLUMING RGH IN 620 630 5 5 JAN2884 FEB0484 FEB0284 FEB0984 7 TRAMMEL
POUR S.O.G. 630 790 8 8 FEB0284 FEB0984 FEB1084 FEB1784 7 WHITE
STAIRCASES 585 590 25 25 DEC1983 DEC1983 JAN1384 JAN1384 0 * CABELL
PLUMB. TOP OUT 630 890 10 10 FEB0284 MAR1384 FEB1284 MAR2384 40 BROOK
ELEC. PULL WIRE & POWER 640 760 10 10 FEB0784 MAR1484 FEB1784 MAR2484 36 GIBSON
ELEC. FIXTURES/SWITCHES/PLUGS 760 960 5 5 FEB1784 MAR2484 FEB2284 MAR2984 36 GENET
STAIR FILL 597 710 10 10 JAN1384 MAR1684 JAN2384 MAR2684 63 KALIN
INSULATION 790 800 2 2 FEB1784 FEB1784 FEB1984 FEB1984 0 * WILSON
DRYWALL 800 810 10 10 FEB1984 FEB1984 FEB2984 FEB2984 0 * PARR
CERAMIC TILE 810 850 20 20 FEB2984 FEB2984 MAR2084 MAR2084 0 * MORRIS
PAINT INTERIOR 810 860 10 10 FEB2984 MAR0984 MAR1084 MAR1984 9 BEREN
DUMMY 860 870 0 0 MAR1084 MAR1984 MAR1084 MAR1984 9 WILCOX
STAIN DOORS 870 920 5 5 MAR1084 MAR1984 MAR1584 MAR2484 9 LOPEZ
FINISH HARDWARE 920 960 5 5 MAR1584 MAR2484 MAR2084 MAR2984 9 BAIR
METAL SIDING 0 890 2 2 OCT4883 MAR2184 NOV1983 MAR2384 125 KRENCHIK
ACCESS LADDER 950 960 5 5 FEB1384 MAR2484 FEB1884 MAR2984 40 LEACH
REGISTERS & GRILLS 955 957 5 5 MAR0884 MAR2284 MAR1384 MAR2784 14 FREEMAN
BALANCE H.V.A.C. 957 960 2 2 MAR1384 MAR2784 MAR1584 MAR2984 14 TRESH
TOILET FIXTURES 850 910 5 5 MAR2084 MAR2084 MAR2584 MAR2584 0 * WERST
TOILET PARTITIONS 910 940 2 2 MAR2584 MAR2584 MAR2784 MAR2784 0 * LOLICH
PAINT STAIRS 710 960 3 3 JAN2384 MAR2684 JAN2684 MAR2984 63 BUNNING
CURBS & SIDEWALKS 650 960 5 5 FEB2284 MAR2484 FEB2784 MAR2984 31 MCCLAIN
FINAL CLEAN UP 960 970 2 2 MAR2984 MAR2984 MAR3184 MAR3184 0 * NORTHRUP
DUMMY 600 620 0 0 JAN2884 JAN2884 JAN2884 JAN2884 0 * STANLEY
ROOF HATCH 890 950 1 1 FEB1284 MAR2384 FEB1384 MAR2484 40 OYLER
DUMMY 587 590 10 10 DEC1983 JAN0384 DEC2983 JAN1384 15 CASH
METAL DECK WELD 587 597 25 25 DEC1983 FEB2084 JAN1384 MAR1684 63 WOCKFUSS
DUMMY 810 955 0 0 FEB2984 MAR2284 FEB2984 MAR2284 22 GRUBB
DUMMY 595 597 0 0 JAN0884 MAR1684 JAN0884 MAR1684 68 COBB
TOILET ACCESSORIES 940 960 2 2 MAR2784 MAR2784 MAR2984 MAR2984 0 * GRENBERG
THE CRITICAL PATH LENGTH IS 135
COMPLETE LIST OF CRITICAL PATH ACTIVITIES (THOSE ACTIVITIES DENOTED ABOVE BY *)
ACTIVITY DESCRIPTION FROM NODE TO NODE DURATION CUM.TIME
----------------------------------------------------------------------------
MOBILIZATION 500 510 2 2
GRADE & CLEAR 510 520 5 7
REBAR PIERS 520 530 5 12
POUR PIERS 530 550 5 17
EXCAVATE FOUNDATIONS 550 560 8 25
REBAR FOUNDATIONS 560 570 5 30
ANCHOR BOLTS 570 580 2 32
POUR & CURE FOUNDATIONS 580 585 0 32
STAIRCASES 585 590 25 57
DECK FILL CONCRETE 590 600 15 72
DUMMY 600 620 0 72
ELEC. RGH. IN 620 640 10 82
MAIN ELEC PANEL 640 790 10 92
INSULATION 790 800 2 94
DRYWALL 800 810 10 104
CERAMIC TILE 810 850 20 124
TOILET FIXTURES 850 910 5 129
TOILET PARTITIONS 910 940 2 131
TOILET ACCESSORIES 940 960 2 133
FINAL CLEAN UP 960 970 2 135
PATH ENDS AT NODE 970
CRITICAL PATH NUMBER 2 STARTING AT NODE 600
WALL FRAMING 600 790 20 92