  1.                     CRITICAL PATH ANALYSIS FOR: P&L CONSTRUCTION PROJECT RUN DATE: OCT 28 , 1983
  2.  
  3.                                              TIME PERIOD = CALENDAR DAYS
  4.  
  5. ACTIVITY DESCRIPTION                     FROM   TO  EST. ACTUAL  EARLY    LAST     EARLY    LAST  FLOAT C REPORT  SUBCONTRACTOR
  6.                                          NODE  NODE TIME  TIME   START    START    FINISH  FINISH  TIME P FINISH      NAME
  7.  
  8. MOBILIZATION                              500  510    2     2   OCT4883  OCT4883  NOV1983  NOV1983    0 *         WILSON      
  9. GRADE & CLEAR                             510  520    5     5   NOV1983  NOV1983  NOV2483  NOV2483    0 *         JONES       
  10. REBAR PIERS                               520  530    5     5   NOV2483  NOV2483  NOV2983  NOV2983    0 *         MILLER      
  11. POUR PIERS                                530  550    5     5   NOV2983  NOV2983  DEC0483  DEC0483    0 *         ARCHS       
  12. EXCAVATE FOUNDATIONS                      550  560    8     8   DEC0483  DEC0483  DEC1283  DEC1283    0 *         LEMON       
  13. REBAR FOUNDATIONS                         560  570    5     5   DEC1283  DEC1283  DEC1783  DEC1783    0 *         BUGMAN      
  14. ANCHOR BOLTS                              570  580    2     2   DEC1783  DEC1783  DEC1983  DEC1983    0 *         SHECK       
  15. POUR & CURE FOUNDATIONS                   580  585    0     0   DEC1983  DEC1983  DEC1983  DEC1983    0 *         WILLIS      
  16. STRUCTURAL STEEL                          585  587    0     0   DEC1983  JAN0384  DEC1983  JAN0384   15           MEAD        
  17. DECK FILL CONCRETE                        590  600   15    15   JAN1384  JAN1384  JAN2884  JAN2884    0 *         KNOUS       
  18. WELD STRUCTURAL                           587  595   20    20   DEC1983  FEB2584  JAN0884  MAR1684   68           HOM         
  19. FIRE PROOFING                             620  625    5     5   JAN2884  FEB2884  FEB0284  MAR0484   31           HEDIN       
  20. PRECAST PANELS                            625  650   20    20   FEB0284  MAR0484  FEB2284  MAR2484   31           ROBER       
  21. P.M. FRAMES                               600  790    2     2   JAN2884  FEB1584  JAN3084  FEB1784   18           MAST        
  22. WALL FRAMING                              600  790   20    20   JAN2884  JAN2884  FEB1784  FEB1784    0 *         JONEY       
  23. SHEET METAL DUCTWORK                      600  955   40    40   JAN2884  FEB1184  MAR0884  MAR2284   14           FURRER      
  24. ELEC. RGH. IN                             620  640   10    10   JAN2884  JAN2884  FEB0784  FEB0784    0 *         MACFORD     
  25. MAIN ELEC PANEL                           640  790   10    10   FEB0784  FEB0784  FEB1784  FEB1784    0 *         MCCALL      
  26. PLUMING RGH IN                            620  630    5     5   JAN2884  FEB0484  FEB0284  FEB0984    7           TRAMMEL     
  27. POUR S.O.G.                               630  790    8     8   FEB0284  FEB0984  FEB1084  FEB1784    7           WHITE       
  28. STAIRCASES                                585  590   25    25   DEC1983  DEC1983  JAN1384  JAN1384    0 *         CABELL      
  29. PLUMB. TOP OUT                            630  890   10    10   FEB0284  MAR1384  FEB1284  MAR2384   40           BROOK       
  30. ELEC. PULL WIRE & POWER                   640  760   10    10   FEB0784  MAR1484  FEB1784  MAR2484   36           GIBSON      
  31. ELEC. FIXTURES/SWITCHES/PLUGS             760  960    5     5   FEB1784  MAR2484  FEB2284  MAR2984   36           GENET       
  32. STAIR FILL                                597  710   10    10   JAN1384  MAR1684  JAN2384  MAR2684   63           KALIN       
  33. INSULATION                                790  800    2     2   FEB1784  FEB1784  FEB1984  FEB1984    0 *         WILSON      
  34. DRYWALL                                   800  810   10    10   FEB1984  FEB1984  FEB2984  FEB2984    0 *         PARR        
  35. CERAMIC TILE                              810  850   20    20   FEB2984  FEB2984  MAR2084  MAR2084    0 *         MORRIS      
  36. PAINT INTERIOR                            810  860   10    10   FEB2984  MAR0984  MAR1084  MAR1984    9           BEREN       
  37. DUMMY                                     860  870    0     0   MAR1084  MAR1984  MAR1084  MAR1984    9           WILCOX      
  38. STAIN DOORS                               870  920    5     5   MAR1084  MAR1984  MAR1584  MAR2484    9           LOPEZ       
  39. FINISH HARDWARE                           920  960    5     5   MAR1584  MAR2484  MAR2084  MAR2984    9           BAIR        
  40. METAL SIDING                                0  890    2     2   OCT4883  MAR2184  NOV1983  MAR2384  125           KRENCHIK    
  41. ACCESS LADDER                             950  960    5     5   FEB1384  MAR2484  FEB1884  MAR2984   40           LEACH       
  42. REGISTERS & GRILLS                        955  957    5     5   MAR0884  MAR2284  MAR1384  MAR2784   14           FREEMAN     
  43. BALANCE H.V.A.C.                          957  960    2     2   MAR1384  MAR2784  MAR1584  MAR2984   14           TRESH       
  44. TOILET FIXTURES                           850  910    5     5   MAR2084  MAR2084  MAR2584  MAR2584    0 *         WERST       
  45. TOILET PARTITIONS                         910  940    2     2   MAR2584  MAR2584  MAR2784  MAR2784    0 *         LOLICH      
  46. PAINT STAIRS                              710  960    3     3   JAN2384  MAR2684  JAN2684  MAR2984   63           BUNNING     
  47. CURBS & SIDEWALKS                         650  960    5     5   FEB2284  MAR2484  FEB2784  MAR2984   31           MCCLAIN     
  48. FINAL CLEAN UP                            960  970    2     2   MAR2984  MAR2984  MAR3184  MAR3184    0 *         NORTHRUP    
  49. DUMMY                                     600  620    0     0   JAN2884  JAN2884  JAN2884  JAN2884    0 *         STANLEY     
  50. ROOF HATCH                                890  950    1     1   FEB1284  MAR2384  FEB1384  MAR2484   40           OYLER       
  51. DUMMY                                     587  590   10    10   DEC1983  JAN0384  DEC2983  JAN1384   15           CASH        
  52. METAL DECK WELD                           587  597   25    25   DEC1983  FEB2084  JAN1384  MAR1684   63           WOCKFUSS    
  53. DUMMY                                     810  955    0     0   FEB2984  MAR2284  FEB2984  MAR2284   22           GRUBB       
  54. DUMMY                                     595  597    0     0   JAN0884  MAR1684  JAN0884  MAR1684   68           COBB        
  55. TOILET ACCESSORIES                        940  960    2     2   MAR2784  MAR2784  MAR2984  MAR2984    0 *         GRENBERG    
  56.  
  57.  THE CRITICAL PATH LENGTH IS 135 
  58.  COMPLETE LIST OF CRITICAL PATH ACTIVITIES (THOSE ACTIVITIES DENOTED ABOVE BY *)
  59.  
  60.  ACTIVITY DESCRIPTION                   FROM NODE TO NODE  DURATION  CUM.TIME
  61.  ----------------------------------------------------------------------------
  62.   MOBILIZATION                             500      510        2         2
  63.   GRADE & CLEAR                            510      520        5         7
  64.   REBAR PIERS                              520      530        5        12
  65.   POUR PIERS                               530      550        5        17
  66.   EXCAVATE FOUNDATIONS                     550      560        8        25
  67.   REBAR FOUNDATIONS                        560      570        5        30
  68.   ANCHOR BOLTS                             570      580        2        32
  69.   POUR & CURE FOUNDATIONS                  580      585        0        32
  70.   STAIRCASES                               585      590       25        57
  71.   DECK FILL CONCRETE                       590      600       15        72
  72.   DUMMY                                    600      620        0        72
  73.   ELEC. RGH. IN                            620      640       10        82
  74.   MAIN ELEC PANEL                          640      790       10        92
  75.   INSULATION                               790      800        2        94
  76.   DRYWALL                                  800      810       10       104
  77.   CERAMIC TILE                             810      850       20       124
  78.   TOILET FIXTURES                          850      910        5       129
  79.   TOILET PARTITIONS                        910      940        2       131
  80.   TOILET ACCESSORIES                       940      960        2       133
  81.   FINAL CLEAN UP                           960      970        2       135
  82.  
  83.                        PATH ENDS AT NODE 970 
  84.  
  85.                         CRITICAL PATH NUMBER 2 STARTING AT NODE 600 
  86.  
  87.   WALL FRAMING                             600      790       20        92
  88.